Power : Calleya Estate HV Feeder Cable
KIER was asked to assist with the installation of 2km of 160PE electrical conduit for the installation of the Calleya Estate HV Feeder cable in the Perth Metro South East Region. KIER utilised its Vermeer 36x50DRii with 210m of drill rods in order to complete 200m drill shots (2 rolls of conduit) at a time. The project was completed in just over 11 days with an average daily throughput of 200m including all road crossings and pipe link-ups.
KIER Scope of Works
- Service Location / Potholing
- Installation of 160mm HPDE electrical pipe by horizontal directional drilling techniques.
- Aligning pipe to enable cable hauling
- Breakout & Reinstatement of concrete, brick & landscaped areas.
Project
Calleya 400HV Feeder
Main Contractor
Underground Services
for Stockland.
Project Timing
2015
OHS & E
Zero LTI's
NBN : Perth Metro, WA
KIER is currently involved in the construction of several Fibre Distribution Areas (FDA) across multiple Fibre Serving Area Modules (FSAM) for the NBN in and around Perth Metropolitan Area, Western Australia. The work is on brownfield sites, where next to the new installation of pits and conduit, the existing telecom infrastructure needs to be tested and repaired. The KIER civil works in these areas are currently proceeding within budget and ahead of schedule.
Project
National Broadband Network
Main Contractor
Syntheo JV/Lendlease for NBN Co.
Project Timing
2013 / 2014
OHS & E
Zero LTI's
KIER Scope of Works
- Installation of 50mm and 100mm telecom conduit though open cut trenching.
- Installation of 63mm and 110mm HPDE pipe by horizontal directional drilling techniques (local and transit links).
- Service Location
- Pit Link-Ins
- Removal and renewal of telecom pits.
- Rod, Rope and Reparation of existing telecom infrastructure.
- Reinstatement of concrete, brick & landscaped areas.
- Flushing and cleaning of existing pits and conduits.
Wastewater : Robertson, NSW
A 25km underground (infill) sewerage reticulation pipe network in and around Robertson, NSW. The project required the installation of a gravity and pressure pipe network, pump station, sewerage treatment plant and storage dam. Robertson lies within the Sydney Water Catchment area, resulting in strict environmental controls. The location and heavy rainfall during the project also resulted in a high water level meaning substantial dewatering was necessary.
Project
Robertson Sewerage Scheme
Main Contractor
AJ Lucas with NSW Public Works
Project Timing
2011 - 2013
OHS & E
Zero LTI's
KIER Scope of Works
Excavation and laying of 150mm - 300mm PVC gravity sewer pipe at depths from 1.5 metres to 6 metres, including dewatering, placement of house connections and restoration.
Installation of HDPE pressure sewer (up to 315mm) through directional drilling techniques.
Installation of access chambers to the sewer network.
Earthworks and installation of a 10 metre deep pumping station (3.6 metre diameter).
Excavation and construction of a 1.5km rising main connecting the pumping station to the newly built sewerage treatment plant.
Earthworks : Bedfordale, WA
KIER was contracted to perform all site works on a 1 acre block in Bedfordale, WA. The site consisted of substantial areas of rock which needed to be broken out. KIER also needed to import around 500m3 of clean sand for the residential and garage sand pads. The site was completed ahead of schedule and with no changes to the costs for the client.
Project
Siteworks
Bedfordale, WA
Main Contractor
Preparation for
Ross North Builders
Project Timing
2014
OHS & E
Zero LTI's
KIER Scope of Works
Liaise with the local council
Cutfill block as per Sspecification
Breakout of Rock
Level Block to specification
Leave sand pad in readiness for builder as per drawings
Build subsoil drainage
Build retaining walls
Excavate driveway and install a sandstone base
Supply & Install septic tanks as specified & leave connection point for builder
Supply & Install Soak Wells tanks as specified and leave connection point for builder
Install Service Trench to house as specified.